TENDERS
TENDER
NOTICE
“LAYING,
SPLICING, TERMINATION AND TESTING
OF OPTICAL FIBRE CABLE” in PABLIKHAS – BAMAN HERI and BAMAN
HERI - SAHARANPUR section for RailTel – Northern Region
Tender
Notice No. RCIL/NR/PAB - SRE/21/T-02/2005
Dated 13.01.2005
RailTel Corporation of India Limited
(A Govt. of India Enterprise)
Regional Office: 3rd floor, Microwave Tower Complex,
Railway colony, Thompson road, New Delhi-110002.
1. RailTel Corporation
of India Ltd.(RailTel) invites sealed tenders under Two Packet
system from established contractors with proven experience for the
work of “Laying, Splicing,
Termination and Testing of Optical Fibre Cable” in the following
Sections of Northern Railway
for RailTel- Northern Region:-
| S. No. |
Section |
Distance |
Estimated cost |
| 1 |
Pablikhas – Baman Heri |
51 RKm |
Rs 30.18 lacs |
| 2. |
Baman Heri - Saharanpur |
53 RKm |
Rs 30.81 lacs |
2. Details of the tender are as under:
| a) |
Sale of Tender Documents |
13-01-2005 to 04-02-2005 (1200
Hrs)
|
|
b) |
Receipt of tender documents |
upto 04-02-2005 (1500 Hrs)
|
|
c) |
Opening of tender documents |
04-02-2005 (1600 Hrs)
|
|
d) |
Earnest Money (EMD) |
Rs 25,000/- for each section
separately
|
|
e) |
Completion Period |
60 days
|
|
f) |
Cost of Tender Document |
Rs 1,000/- (Rs. One thousand only) and
Rs 1,200/- (One thousand two hundred only), if required by post. |
|
g) |
Tender document may be obtained from the office of RailTel Corp. of India
Ltd at the address mentioned above by paying the cost of the Tender
Documents through Pay Order/Bank Draft in favour of RailTel Corporation
of India Limited, New Delhi. RCIL shall not be responsible for late receipt of
Tender document if any postal delay if required by post. |
3. Due preference will be given to Public Sector Undertakings as per extant rules, applicable
on the day of opening of this tender.
4. Tender Notice and Tender Document is also available on RailTel’s website and can be
downloaded from www.railtelindia.com
. The cost of the tender document shall however have to be deposited along with the Tender bid (Technical) – Part-I, in form of Demand
Draft/ Pay Order as detailed above in 2 (f).
General
Manager
Northern Region
Click here to
download the Tender Notice and Tender Documents >>
Top
|